Engineer on your side
Client's engineer for solar, storage and open-access power
When someone else builds it, hire us to check it. As your engineer on a project we do not build, supply or sell power on it, so our only interest is that the right plant is built and performs for its whole life.
In short
The problem
A project is on the table with a payback that looks compelling. The model was prepared by a party who benefits from it proceeding, and the assumptions that will actually determine the outcome — yield, load profile, regulatory route, grid access, battery safety, contract structure — sit in cells nobody has independently tested.
Why it matters
This is a twenty-five year commitment. The consequences of getting it wrong do not appear at handover, when they could still be argued about. They appear years later, by which time the performance guarantee has expired, the contractor has moved on, and the capital is sunk.
Who typically needs this
- Manufacturers evaluating rooftop, ground-mount, open-access or group-captive solar
- Data centres adding solar and battery storage on a fixed build programme
- Public bodies and PSUs procuring energy assets under audit
- Developers and concession holders who need an independent engineer
- Investors and lenders requiring technical due diligence
- Owners with a project already underway that is not going to plan
Scope
- Feasibility and business case
- Owner's requirements and technical specification
- Battery storage sizing and fire-safety specification
- Open-access, net-metering and connectivity applications
- Group-captive evaluation
- Tender documents and bid evaluation
- Design review, vendor audits and FAT
- Construction supervision on your behalf
- Commissioning witness and performance-guarantee verification
- Post-commissioning advisory
- Technical due diligence for lenders and investors
Energy projects rarely fail for interesting reasons.
They fail because a system was sized against sanctioned load instead of the interval curve. Because a yield figure was taken at P50 and never stress-tested. Because the contract left a gap between the civil and electrical scope that nobody owned until it mattered. Because acceptance was granted on a good day in April rather than on a performance test over a representative period.
Each of these is knowable in advance. None of them is a technology problem.
What a client’s engineer is for
On this kind of project we are not the contractor. What an owner is buying at the point of decision is a defensible view of what the asset will produce, what it will cost, what could go wrong, and who carries each risk. A client’s engineer produces that view and then holds the contractor and the equipment makers to it, from the first load study to the performance test.
That is why the most valuable finding in an early assessment is often that the project should be smaller, structured differently, or not built at all.
Solar, storage and open access
The scope covers rooftop and ground-mount solar, battery energy storage — including the fire-safety specification for lithium-ion systems — and the open-access, net-metering and group-captive routes that decide whether the economics work at all.
One role per project
We work in two ways. As your engineer, we sit on your side of the table. Under a RESCO, PPA or group-captive arrangement, we offer you the power itself at an agreed tariff.
The two are never combined. On any given project we declare in writing which role we hold, and we do not supervise or evaluate ourselves.
What you actually receive
Services describe activity. These are the artefacts that exist at the end, and that you own.
-
Feasibility assessment
Technical and commercial viability with yield stated at P50 and P90, sizing derived from the interval load curve, and the regulatory route confirmed for your state rather than assumed.
-
Financial and commercial model
A working model handed to you, not a summary of outputs. Sensitivities on tariff trajectory, yield, degradation and surcharge exposure, with the breakpoints identified — the values at which the case stops working.
-
Owner's requirements and technical specification
Specifications for modules, inverters, battery chemistry, power conversion, protection and grid interconnection, written before tender rather than adapted from a bidder's proposal, with the scope interfaces explicitly assigned.
-
Battery storage and fire-safety specification
Sizing against the actual tariff structure and load profile, cycling reconciled against warranty terms, and the fire and thermal-runaway safeguards specified as requirements that bidders must price and meet.
-
Open-access and group-captive evaluation
Route comparison including banking rules, surcharge exposure and the ongoing compliance obligations of each structure, including the annual criteria a group-captive arrangement must keep meeting.
-
Bid evaluation
Evaluation on lifetime cost, contractor delivery record and financial standing. A materially low bid is treated as a risk indicator rather than a saving.
-
Construction and commissioning record
Inspection at defined hold points, factory acceptance, non-conformances tracked to closure, and a witnessed performance-guarantee test over a representative period.
-
Technical due diligence
Independent assessment for lenders, investors or acquirers, written on the assumption that another engineer will scrutinise it.
How we approach the work
-
We ask whether the project should exist before asking how to build it
The most valuable output of an early assessment is often a recommendation not to proceed, or to do something smaller. Energy efficiency, load shifting, or a contract renegotiation can deliver a large share of the benefit without the capital. A firm that only earns when the project proceeds will not tell you this.
-
Yield is stated at P90, not only at P50
A P50 estimate is a coin flip. We state both, name the data source, and model soiling and degradation to site conditions rather than adopting a standard loss table. Where the case only survives at P50, that is the finding.
-
Sizing follows the interval load curve, not the connected load
Self-consumption is determined by the 15-minute profile — shift patterns, seasonal variation, weekly shutdowns — not by sanctioned load. Oversizing produces export at a tariff that makes the payback collapse, and it is not recoverable after commissioning.
-
Battery safety is a specification, not an inspection
Lithium-ion storage carries real fire and thermal-runaway risk. We write the safeguards into the owner's requirements, check them at factory acceptance, and verify them on site, so safety is priced by bidders rather than argued about after installation.
-
The regulatory route is a design input, not a compliance step
Captive, group-captive, open-access and third-party structures each carry different surcharge exposure, banking rules and ongoing obligations that vary by state and change during a project's life. Group captive in particular depends on equity and consumption criteria being maintained every year.
How a project advances
Projects move through defined gates. Each has a question it exists to answer, the evidence required to pass, and the condition under which we would recommend stopping.
- 01
Concept screening
Is there a plausible case at all, and is this the right intervention?
Evidence to pass
Interval load data, current tariff structure and its trajectory, available roof and land, indicative regulatory route.
We would stop if
The load profile does not support meaningful self-consumption, the tariff arbitrage is thin, or an efficiency measure would deliver most of the benefit for a fraction of the capital.
- 02
Pre-feasibility
What size and structure, and does the regulatory route actually exist here?
Evidence to pass
Preliminary yield estimate, sizing against the 15-minute load curve rather than connected load, indicative capex, comparison of captive, group-captive, open-access and third-party routes for your state.
We would stop if
The regulatory route carries a policy risk you cannot absorb, or grid evacuation capacity is unavailable within the required timeline.
- 03
Feasibility and business case
Does it clear the hurdle rate on assumptions we are willing to defend?
Evidence to pass
Yield stated at both P50 and P90, soiling and degradation modelled to site conditions, full model with sensitivities and breakpoints, land title and connectivity confirmed.
We would stop if
The case only works at P50 with no headroom, land or title cannot be cleared, or the payback depends on a tariff assumption with no regulatory support.
- 04
Investment decision
Is the risk allocation acceptable, and who carries what?
Evidence to pass
Contract structure, performance-guarantee terms, liquidated-damages caps tested against real exposure, insurance, and the ongoing compliance obligations of the chosen structure.
We would stop if
Liquidated damages are capped too low to change contractor behaviour, or performance guarantees expire before degradation would become visible.
- 05
Procurement
Are we buying capability or buying a number?
Evidence to pass
Technical specification written before tender, bid evaluation on total lifetime cost, contractor financial and delivery-record assessment.
We would stop if
The lowest bid is materially below the others, which usually means scope has been dropped or the contractor is under-bidding to secure work.
- 06
Construction
Is what is being built what was specified?
Evidence to pass
Inspection at defined hold points, factory acceptance and material verification, non-conformance tracked to closure rather than to acknowledgement.
We would stop if
Substitutions are made without engineering approval, or non-conformances accumulate faster than they close.
- 07
Commissioning
Does it perform, measured properly?
Evidence to pass
Performance ratio tested over a representative period under agreed irradiance conditions — not a single good day. Capacity and availability tests witnessed. Punch list closed before final acceptance.
We would stop if
Acceptance is being sought on a demonstration rather than a test, or on a period unrepresentative of operating conditions.
How a project runs
Our full delivery model →The client's-engineer scope runs in seven stages. An engagement can start at any of them, and every one runs on the same governance: one accountable partner, a fixed reporting cadence, a live risk register and a decision log.
We can be engaged at any stage, including on a project already in construction that is not going to plan, where the first task is establishing what is actually true.
- 01 Feasibility & business case
- 02 Owner's requirements & basic engineering
- 03 Regulatory support
- 04 Tendering & procurement
- 05 Design review, vendor audits & FAT
- 06 Construction supervision & commissioning
- 07 Post-commissioning advisory
- One role per project, declared in writing
- One accountable partner, end to end
- Stop conditions agreed before the work starts
Who this is for, and what they arrive with
-
Manufacturing
Energy among the top three controllable costs, with captive and open-access options poorly compared and usually evaluated by whoever is selling one of them.
-
Data centres
Solar and battery storage on a build programme that will not move, with battery fire safety and statutory approvals on the critical path.
-
Government & PSUs
Procurement that must be technically defensible under audit years later, with specifications written before tender rather than adopted from a preferred bidder.
-
Infrastructure & developers
Financing conditional on technical diligence that a lender's own engineer will scrutinise.
-
Investors & lenders
Technical diligence where the financial model's weakest assumptions are engineering ones the deal team cannot independently assess.
How we hold ourselves to it
- One role per project, declared in writing. If we are your engineer, we are not bidding and we are not offering you power on the same project.
- On a project where we are your engineer we do not build it, supply its equipment or sell you its power, so our advice is aligned only with your interest. Arohan does build systems as an EPC contractor, but never on a project it is checking.
- Battery fire safety written into the specification and verified in the field, not discovered at an audit at the end.
- Performance assessed against asset life rather than against commissioning day.
Questions buyers ask about this work
When should a project NOT proceed?
When the case only clears the hurdle rate at P50 with no headroom. When the load profile does not support self-consumption and the export tariff is where the payback actually lives. When grid evacuation is not available within the build window. When land title or conversion is unresolved and being treated as a formality. And when an efficiency measure or a tariff renegotiation would deliver most of the benefit without the capital.
What are the most common reasons these projects fail?
Sizing against connected load rather than the interval curve; yield assumptions taken at P50 and never stress-tested; regulatory or surcharge changes the model had no headroom to absorb; interface gaps between civil, electrical and grid scope; acceptance granted on a demonstration rather than a performance test; and no internal owner of asset performance after handover. Almost none of these are equipment failures.
Can you work with our existing EPC contractor?
Yes. Acting as client's engineer alongside a contractor you have already selected is straightforward, and our independence is the point: we are not bidding for the construction scope, and we do not offer you power on a project where we are your engineer.
Can you review a project that is already underway?
Yes. An independent review mid-construction is worth more than one after handover, because there is still time to act. The first step is establishing what is actually true rather than what is being reported — measured progress, non-conformance status, and whether the contract still protects you given where the project has reached. Some troubled projects should be completed to a lower specification, and some should be stopped; we will tell you which.
How do you handle battery fire safety?
As a requirement from the first specification: chemistry, container design, detection and suppression, separation and access are written into the owner's requirements, checked at factory acceptance, and verified on site before energisation.
Arohan also does EPC. Could you end up building the project you are checking?
No. Arohan does build systems as an EPC contractor, but on a project where we are your engineer we do not build it, supply its equipment or offer you its power, and that role is written at the top of the proposal. If you want us to build it instead, that is a different engagement, and you would then appoint someone else as your engineer.